12m manual concrete placing boom Installation Precautions
1. When we install the 12m concrete placing boom, carefully inspect each part and pipe buckle.
2. When using the spreader, carefully check the spreader used.
3. When the 12-meter concrete placing boom is placed on the top plate of the formwork, we must first select the position where the concrete placing boom is placed and reinforce the four feet of the concrete placing boom. At this time, to be noted that the reinforcement of the top plate to be reinforced in the template, according to the size of the concrete reinforcement cloth
and sized feeder
4. When the reinforcement is completed, put down the 12-meter concrete distributing machine, and fasten the cable wind rope, and then lift the weight of the concrete distributing machine to ensure the balance and stability of the concrete distributing machine.
5. When using the 12-meter concrete placing boom for concrete pouring, the fabric of the cloth boom is used, and the base of the cloth boom and the steel pipe for the fixed frame are fixed firmly to ensure that the cloth boom is stable, not shaken or tilted when transporting.
6. When pouring concrete with a 12-meter concrete concentrating machine, it is necessary to carry out follow-up inspection on the concrete concentrating machine. If problems are found, the watering should be stopped immediately, and immediately rectified, and no concrete safety hazards should be confirmed before pouring concrete.
7. When the concrete is poured using the 12-meter concrete placing boom, the concrete of the concrete distributor should be cleaned first. After the cleaning is completed, the concrete placing boom is hoisted with the tower crane, and the installation is stable and the cable wind is pulled. rope.